Project Progress

Project Kick-Off Meeting (10/8/2024)

COMPLETE

Meeting with Stakeholders (1/16/2025)

COMPLETE

Public Meeting (2/25/2025)

Scheduled

Data Collection (March 2025)

In Progress

Develop BSIP Goals and Objectives (April 2025)

In Progress

Field Assessment (March 2025)

In Progress

Bus Stop Improvement Identification (May 2025)

Not Started

Feasibility Review (June 2025)

Not Started

Funding Analysis and Project Prioritization (July 2025)

Not Started

Prepare Bus Stop Improvement Plan (October 2025)

Not Started

Presentation to Board of Commisioners (November 2025)

Not Started